Proposed Biogas plant could bleed Gort dry

Last week An Bord Pleánala wrote to the applicants for the proposed Biogas plant in Gort seeking clarifications regarding its water supply requirements. The developers state that they will need 120,000 m³ (120 million litres) of water annually to run the plant and there are some major concerns over this.

Why is this important?

The Biogas proposal would have a significant impact on the water supply of Gort Town which already has a constrained capacity. An additional extraction of 120 million litres per year would break an already over-stretched infrastructure. In order to meet these Biogas demands, significant restrictions could be imposed on the Gort Town Water Supply on how we could use water domestically, in businesses as well as potentially constraining future planning potential.

120,000 m³ of water is 120 million litres, which is Croke Park flooded to a depth of 10 metres. This relates to an average of 328 m³/day.

Why does a Biogas plant consume so much water?

In order to get an optimum aerobic digestion process, feedstock (silage, slurry, food waste) needs to be the consistency of a wet-sludge. The applicants state that the proposed Biogas plant will need sludge with dry-mater content (DMC) of between 5% and 8%.  

The proposal indicates that it will process 90,000 tonnes of feedstock, including 54,000 tonnes of silage, which has a very high dry-matter content (28%), and would need to be diluted 3-fold to achieve the ideal ratio. This means evert cubic metre of silage (0.77 tonnes) would need about 3000 litres of water to dilute it correctly. So even with silage alone this would be well over 120 million litres water/year, and not considering dilution of the remaining 36,000 tonnes of feedstock. Their estimation is therefore too low for the proposed development.

An important point to note is that the water consumption will not be flat and there will be peaks, mainly from when silage cutting happens from end of May to October. In these months the majority of this water requirement will be consumed. 

What are the Biogas developers proposing?

That’s the thing – the developers have indicated that the need 120 million litres of water per year but have not clarified where they are getting if from or how much they need. They have indicated that they can store run-off water from the site in attenuation ponds but this will only cover.a fraction of the requirements at peak

This is a significant omission that we highlighted during our observations on the application and we are happy that An Bord Pleánala have asked for clarification.

What clarifications are the ABP looking for ?

An Bord Pleanala have rightly questioned the developers to confirm if the capacity of the existing water network is capable of providing their needs.  They requested the following in a letter on 11th May 2022:

“Please provide a breakdown of the water supply source to be utilized at the proposed development, with the associated calculations which confirm the availability of water capacity t othee the state requirements of 120,000 cubic metres of liqour per annum.

What is the capacity of the Gort Water Supply?? 

According to the EPA , 2,638 people are serviced by the Gort Public Water Supply (PWS). The water is sourced mainly from Gort River, supplemented with water from two boreholes.

According to Irish water, the Gort Water supply is constrained and will need improvements to meet growing demand in the next 10 years. The daily demand in 2019 for the Gort Water Supply was 1018 m³/day (~1 million litres) and the expected growth in demand over the next decade is an additional 26,000 litres/day. The water supply is so limited currently that this tiny increase, will require improvements to the network. If an increase of 26,000 litres/day will require a upgrade, what on earth will happen when the proposed Gort Biogas plant needs an extra 328,000 litres/day on top of this. This is a daily average over the year so in peak silage season the requirement could easily double to 650,000 litres/day.

What we can also see from the Irish Water Capacity Register is that currently, in dry summers the Gort Water supply is barely able to keep up with demand. The total capacity of the current water supply is 1,440,000 litres/day and the 2019 demand in summer was 1,407,000 litres/day, allowing only a tiny margin of headroom (33,000 litres/ day) .

The town’s water supply is currently at capacity and burdening the supply further will only result in one thing- water restrictions. So then granting access a massive water consuming plant to use this already highly constrained water network would be simply negligent.

What kinds of impact could this have?

The proposed Gort biogas plant would cause a breakdown of the water supply in normal years and in dry years would wreak havoc. Gort would simply run out of water at peak times.

We are currently 3 months in to a ‘boil notice’ period and are fully aware of the inconvenience and hardship this has brought to some. If the proposed Biogas plant goes ahead, we could easily see 3 months of water restrictions during peak times limiting how and when we use our home supply.

We also need to carefully consider and be fully aware of how this could impact future developments within the town. If the Biogas plant went ahead then it would be impossible to develop more housing because the water supply would not have the capacity. 

There is also the environmental question,- what happens if we take an additional 650,000 litres /day from the Gort River? Will it stop flowing completely (like it almost did in 2018) ?

It’s simply not good enough that the proposed Gort Biogas plant could go ahead without due consideration to these matters. The developers omitted this consideration in their EIAR, we highlighted this on our observations and now An Bord Pleanala is seeking clarification.

The water capacity constraints are very real and so it’s is very unlikely that the Biogas developers will get any confirmation from Irish Water with demands of an additional 120 million litres of water per year day from a water supply that’s on the edge of collapse. We look forward to how the developers intend to address their response to the Bord and we will be ready to challenge it.

This is one of many reasons that this the Gort Biogas Plant can not go ahead. No ifs, no buts. This is a serious consideration, and one of many as equally serious, that could affect the people of this community and the future of the town.

Support is essential !

Please continue to support our fight against this development and share this information far and wide. If An Bord Pleanala allow this development to go ahead then we will need that support even more.

David Murray.

Biogas plant and Cycleways

When the Biogas developers came to town they talked the talk. There was jobs to be had, economic benefits, environmental benefits etc. It sounded like the ‘best-thing’ to happen to Gort since sliced-pan. It sounded really plausible, something, perhaps, beneficial to the area as there wasn’t much else going on for Gort.

It’s only when we scraped the surface and dug a little deeper did we realise the disaster on our doorstep. The proposed Gort biogas plant ended up as the proverbial bowling ball that would obliterate the economic future of South Galway. Here are some key points:

  • The site was within 10m of Gort River and developer admitted in the EIAR that though it was unlikely there would be accidents – an accident would be detrimental to our special areas like Kiltartan, Coole Lake, Garyland and even Galway Bay.
  • An air exhast design flaw that was subject to EPA controversy, in their sister plant in Ballybofey, was also included in the Gort biogas proposal, meaning that the environmental analysis was flawed
  • Their water requirements would have left Gort with a severe water shortage but they deemed that it would have not impact.
  • The traffic analysis was flawed and didn’t account for the disposal of 150,000 tonnes of (very smelly) digestate waste that was to be spread on farms in the immediate vicinity.
  • They tried to downgrade the amenity and recreational aspects of the area indicating that area had little or no recreational value.

There would be … 20 people (over 3 shifts) created.

The sister company’s track record speaks for itself as it was subject to EPA blacklisting and many EPA Non-conformance incidents in the Sister plant. Most of the complaints filed were due to the smell of the plant. The smell covered a huge area and had been highlighted by residents in the Inishowen peninsula. Here is a excerpt from a public meeting regaring the ongoing smell across the south inishowen peninsula.

Residents and business owners filled Burt Hall to full capacity on Thursday night to express their views over the ongoing smell in South Inishowen. 

3 years ago, this was potentially the best thing to happen to South Galway! But … not any more!

Gort River Walk

As the developers tried to downgrade the recreational value of the area, the community was busy progressing the Gort River Walk. This has been earmarked in Gort area plan as part of an amenity network along the Gort River. This hidden gem was really just waiting to be discovered and 3 years after its initial mooting, it is now a key amenity and resource for Gort, South Galway and North Clare.

Cycleway coming to town!

In the last few weeks Gort and South Galway has been selected as the emerging preferred route for the Athlone- Galway cycleway. A potential (and favoured) route of the Cycleway is to follow the Gort River Walk out Lavally, come over the planned bridge, into Kinincha and then take a right out the Kinincha Road toward Ballinamantan and Coole.

If the Biogas was to go ahead, this potential cycleway route would have run at least 300m along the boundary of the smelliest plant in the province, if not in the country.

If the Biogas plant had already been approved, the Athlone-Galway Cycleway would not be coming through South Galway. Yes – 20 jobs would have been created and yes the area would suffered substantially – but shouldn’t be be thankful for 20 jobs???

20 jobs is a distinct number and yes it’s printed in black and white and but it’s 3 shifts of 8 people. That’s a maximum of 8 people for perhaps for lunchs in Sullivan, The Field, The Gallery Cafe, and Roosters Cafe if they decided to go to lunch.

A cycleway has the potential to bring in 200+ people through the area in a single day, not all would be stopping in Gort and 1/2 might be local.

Both Waterford and the new Limerick Cycleway are reporting 250,000 people annually, about 1/2 are local’s using the route and 1/2 are walkers so this should inject a new tourism potential into South Galway as it currently doesn’t have enough accomodation, rooms, restaraunts, pubs, cafes, services to meet the needs of the cycleway.

That’s the scale of the difference we are talking about – A maximum of 8 biogas plant workers having lunch v’s 100+ people passing through and potentially staying in the area in a single day.

The scary thing is, that on the first application for the Biogas plant .. they almost made it…. It ticked all the boxes – green , environment, economic. The next scariest thing is that An Board Pleanala could still give permission to for the Biogas plant and if its granted then its a disaster for everybody (except the developers)

“They have heard how much of a health impact this has on the community and they need to recognise the massive impact they are having on people.”

Donegal Daily, reporting on impacts of Glenmore Biogas plant on the Ballybofey community.

The Way forward

We are now in 3rd consultation phase of the Galway to Athlone Cycleway and the project team is getting feedback on the best route to pick. This picture shows the emerging cycleway corridor (in blue) and also where the proposed biogas plant is going (in red).

The emerging cycleway route corridor (in blue) and the proposed biogas plant (in red)

The most scenic route for the cycleway is probably along the Pound road, over the bridge to Kinincha and out Ballynamantan.

Gort has recently got €800,000 grant for regeneration and enhancement of the town centre – this is the kind of investment we need in the area not smoke stacks and slurry tankers.

We need to ensure that the Biogas plant is never built here.

David Murray.

Catchment 29 – a wider perspective

Cuanbeo is a recently formed community based organisation with a mission of improving the quality of life, environment, economy and heritage in ‘Catchment 29’.  The group recently published a report (available here) on the economic assessment of the Marine Resources in southeast Galway Bay, the potential for growth and threats.

Here we look at a potential threat that hasn’t been explored- the proposal to build one of the largest Biogas plants in the country adjacent to one of the arteries feeding into inner Galway Bay. 

So what is Catchment 29?

Catchment 29 extends from Galway Docks for -117 km along the coastline to Blackhead in Co Clare. It extends inland to Athenry, Loughrea and Gort including the rivers and groundwater systems that enter the Bay. The report identifies that groundwater and surface water systems in the area are closely interlinked and highlights protection under the EU Habitats directive of areas within the catchment.

So why on earth would you site one of the largest Biogas plants in the country here given the potential consequences?

CSO map showing SAC & SPA areas around Catchment 29

Downstream effects

The report contains a case study (Case Study #3), covering a history of flooding and drainage around the Gort area, and highlights the importance of water quality entering the bay…” to the marine resources, and specifically aquaculture and fisheries in Galway Bay”. Maintaining water quality is identified as a major concern for any flood relief works being carried out. All of which are important points when trying to maintain and enhance protected and sensitive habitats.

Notwithstanding the devastating effects on the people of Gort, let’s take a look at the downstream effects of siting one of the largest Biogas plants in the country within Catchment 29.

Interconnectivity of rivers and underground flows around Gort

The proposed development lies just 10m from the Gort river, one of the main arteries that feed into the Coole-Garryland SAC. This water, in turn, enters the sea in Kinvara Bay via underground flows. Any accidental breach or discharge could potentially result in tens of millions of litres of highly concentrated effluent entering directly into the catchment system, the impact of which would be disastrous both locally and downstream. In practical terms, a facility of this magnitude is a large scale chemical factory first and foremost. For the aquaculture sites, sensitive benthic communities and protected inter-tidal habitats downstream this would be catastrophic and has the potential to not only impact the local coastal economy (fishers, aquaculture sites and the blue economy) but also threaten the protected status of this unique area.

Given the credentials of the sister development in Ballybofey (Glenmore Biogas), its chequered history of ongoing mishaps and calamities (see the Brimstone cowboys), this is a ‘when’ rather than an ‘if’ scenario.

The facility also plans to connect to Gort’s wastewater treatment plant (WWTP), a facility already identified as operating at over-capacity, placing an additional and ongoing load on an already overburdened facility. Another red flag for maintaining water quality in the Coole-Garryland SAC.   

Joined up thinking

The purpose of the report, as defined by the group, is “…to establish a baseline economic value of the marine resources including ecosystem services associated with this catchment, to heighten awareness with policy makers and planners to the true value of the aquatic marine environment…”.

The role of the wider catchment is clear- ensuring the quality of freshwater input is a vital component to maintaining water quality in inner Galway Bay. Sourcing a Biogas plant of this magnitude in such close proximity to the Gort river cannot be justified given the potential consequences.

The report notes the proliferation of community led groups in recent years, as trust waivers in state agencies to provide the degree of protection expected by communities. As custodians of our local environment, the role of community led groups has never been so important in south Galway (see South Galway-an environmental powder keg)

Three years on and the threat of this development is still very much alive. The case is now in the hands of ABP with a decision pending. Let’s hope due consideration is given not only to the implications for the people of Gort but also the downstream consequences for Galway Bay.

South Galway – The Environmental powder keg

Update : Since the publication of this article An Bord Pleanala has refused the ESB Windfarm at Derrybrien substitute consent essentially making it an unauthorized development. ESB have agreed to decommission the windfarm. Between EU Fines and decommission costs will results in loss of 10s of millions of Euro to the Irish taxpayer.

With the recent flurry of climate change commitments, we run the real risk of enabling environmental malpractice and we should learn from lessons of the past from South Galway.

For a relatively small region, South Galway has become a national symbol of environmental malpractice based on ‘green’ developments. It is not just the controversial Derrybrien Windfarm that continues to garner the news but even more recently, a similarly green project (Gort Biogas Plant) has now been proposed. Both projects, through 20 years apart are giving An Bord Pleanála a bit of a nightmare. While long overdue, within the next month or so, An Bord Pleanála will have to make decisions on both of these projects and Europe is watching very closely. While these 2 development projects tick the ‘good for the environment/climate ‘ boxes, we are still paying harshly for the lessons of Derrybrien Windfarm development malpractice. Have An Bord Pleanála and our Government actually learned the lesson?

An Bord Pleanála and the Derrybrien Windfarm

Over 20 years ago An Bord Pleanála backed the application for the development of a Windfarm in Derrybrien Co. Galway and in some aspects went against Local Authority Decisions. Within 3 years, the plan became the focus of an unauthorized development and an environmental disaster; a landslide/mudslide that entered the rivers of South Galway and killed between 50,000 fish and deposited large amounts of sediment into the catchment. The local Derrybrien community had to engage with the European Commission as the ESB and Irish Government didn’t appear interested or supportive in resolving the situation.

In July 2008, the European Court of Justice ruled that Ireland breached the EIA Directive environmental directive as no assessment was carried out ahead of construction of the large-scale 70 turbine project. After an 11-year hiatus of non-action by ESB and the Irish Government, on 12th Nov 2019, the European Court then issued a €5 million fine and a €15,000 daily fine until a retrospective environmental impact assessment (rEIAR) and associated mitigations were complete. The ESB/local authorities finally got around to applying for a ‘substitute consent’ for the windfarm development in August 2020, supported by a rEIAR. This application and its rEIAR is currently with An Bord Pleanála for review and they need to make a decision imminently.

In the past few weeks, the EU fines have now accumulated to over €15 million and the EU Environment commission did its own analysis of rEIAR. Its advice was pretty stark “Based on the technical review of the rEIAR against the requirements of the EIA Directive, it is recommended that further information is provided before the consenting authority can make an informed decision on this application. “ (See more details here).

This was a warning shot to An Bord Pleanála (ABP). The EU Environment commission brought about the court action and are clearly signalling to the An Bord Pleanála that all is not well with the ESB approach. If An Bord Pleanála rejects the EU report recommendations, then they will be kicking a very expensive can down the road as the daily fine of €15,000 will keep accumulating. The ABP/ESB will likely be told to go back to the drawing board and the process will need to be kickstarted again – wasting millions of tax-payer money.

An Bord Pleanála and the Proposed Gort Biogas Plant

As if the windfarm wasn’t enough of a controversy, an application of a mega biogas plant in Gort, South Galway is now also up for review with An Bord Pleanála . The project itself is for a plant capable for processing 90,000 tonnes of feedstock and will produce 120,000 tonnes of waste – all located within a few hundred meters of Gort town center. This application has the same familiar markers as seen by the Derrybrien Windfarm project.

  • It’s a green project and therefore it must must be good for us
  • Its environmental impact assessments are full of holes
  • There is no engagement with the local community to address local concerns

The application got a stark and strong push-back from the local community with hundreds of objections. In January 2020, Galway County Council rejected the planning application for a wide range of reasons – mainly that it wasn’t convinced that traffic impacts and environmental impacts were identified and mitigated correctly. The following gives a very brief summary of the key reasons:

  • The proposed Biogas Plant is located within a 100m of residential areas and close to Gort Town Center
  • It’s 10m from Gort River which feeds a National Park (Coole Park) and Special Areas of Conservation (SACs) 4km away – another environmental disaster in the making…
  • It would cause traffic chaos around the town
  • Many serious errors in the EIAR that render the Environmental Impact Analysis void. (See more details)

An Bord Pleanála on their website state that they are independent, impartial with professionalism and integrity. They have the facts so you would likely conclude that they will not overturn Galway County Councils decision and grant permission within the next few weeks. However, could this decision be influenced by the current climate-change background?

Climate Change

The pressure is on and it all looks ‘Green’. Its on individuals and it’s on governments. Reduce our carbon footprints, invest in climate change strategies.

How the climate lobby crushed debate - spiked

A recent Farmer’s Journal article. highlights that “Producing feedstock for anaerobic digestion (AD) plants will be one of the key measures to reduce agricultural emissions by 2030 according to the Government’s Climate Action Plan.

Should we aim to implement our Climate Action plan ? Absolutely! But don’t throw the environment and communities and planning regulations under the green bus .

This is unfortunately exactly what happened with the Derrybrien Windfarm.

Will history repeat itself?

The Derrybrien Windfarm debacle has not been fully resolved – It’s been 20 years since An Bord Pleanála gave permission, 17 years since ESB kick-started an unauthorized development and 13 years since ESB first refused to do a retrospective mitigation. It was however, only yesterday we added €15,000 to the €15 million fine and we’ll do the same again today and tomorrow. We (not the ESB) are still paying the price for Environmental malpractice that was done 20 years ago.

One thing is clear, if An Bord Pleanála go against local Authority decision and grant planning permission for the proposed Biogas plant in Gort then once again South Galway Community may have to repeat history and rally and challenge the decision all the way to the European Court.

The following was a warning from GreenNews Ireland in Nov 2019 , on the announcement of the massive European fine:

This issue was deemed so severe that the Court took it into account when setting the high penalty for the State. The fines imposed should now act as a big wake-up call for our Government. If not, the next Derrybrien may be just around the corner and would again leave our natural landscape, our biodiversity and our citizens footing the bill for our ongoing failure to adhere to environmental law.

There is a big conflict here and there shouldn’t be. On ‘paper’ there shouldn’t be any chance that Galway County Council’s planning refusal would be overturned. An Bord Pleanála with it’s impartiality have all facts they need to make the right decision here. There remains, however, probably with the legacy of the Derrybrien Windfarm, a lack of trust to do the right thing.


David Murray

References :

A glimpse into our potential future

To meet the demands of social media, the reporting of news, good or bad, has to be a fast and efficient process. To that end, I’ve been tasked to write media statements for both a positive and a negative outcome in advance of the decision by ABP. At first, I thought this would be a fairly straightforward task but as I sit to write I’m projected into two diametrically opposed futures. As with any two-party decision, there are winners and losers. Here’s a glimpse into what the future could hold…

A negative outcome

One future scenario sees a negative outcome, where ABP grants permission and the development goes ahead, I see an entire community shell shocked. People meeting on the street, shuffling awkwardly, looking at the ground, long pauses in conversation not knowing what to say. A wake-like atmosphere, as people come to terms with what lies ahead of them, a daunting, uncertain future. The loss of a loved one or in this instance a loved and cherished thing, like a community and a town irreversibly changed. The people of Gort, the losers in this future scenario, will bear the burden for future generations to come. 

An entire community reminded of the decision every time they draw a breath and inhale the shitty, eggy smell that permeates the air as far away as our beloved Coole. Reminded every time, they leave one of our many fine pubs after a great night with friends and walk home backlit by the flame stack glowing like a North Sea oil rig, higher than our church spire and visible from every quarter. Reminded every time they have to squeeze hard and pull back on a child’s hand as they attempt to cross the road between another slurry laden tanker roaring through the town. Reminded every time of the once peaceful and serene Golden Mile and Riverwalk now framed by the country’s largest slurry plant a stone’s throw from the town.

In the other camp, champagne corks pop and a few people celebrate their victory. The green light, the go-ahead, the all-clear. Excited plans are made for expensive foreign holidays, perhaps a new car or a second or even third holiday home. We won, we got one over on them, we duped the whole town. The celebration of a few to the detriment of many.

It has taken some time to write these words, for no reason other than it’s a future that’s worrying. The celebration of a few to the detriment of many.

A positive outcome

An alternative future scenario sees a positive outcome, where ABP upholds the decision of Galway County Council and permission is refused. The development is refused, quashed, flattened, a dead duck. People cross the road to confirm the news, phones are checked, messages sent. Can it be true? After a three-year fight, is it gone? Can we now move on? Corks are popped that evening, happy smiles all around. Plans are underway, a party, a celebration, a celebration of the power of people. The people of Gort, a steadfast community galvanised into action, not for personal financial gain but for the benefit of all. I can see the party in my mind’s eye, music on the riverwalk on a summers evening, laughter and chatter permeate the air, not an acrid eggy smell.  

These words flow easily, this is the future we want to see.

For now, we will have to wait for ABP to decide our fate. Let’s hope it’s for the benefit of many not the few.

Rude awakening on Biogas plant investments

Green energy – Airport World

The developers behind the Gort Biogas plant are having some interesting financial dynamics recently. Glenmore Generation Limited (GGL), the developers of the Biogas Plant in Ballybofey, the sister company of Sustainable Bio-Energy Limited (proposers of the Gort Biogas plant) has secured permission to waive £37 million in loan repayments due to its funders in a major restructuring plan after recording a pre-tax loss of £23.6m in 2019. According to a report the accounts reveal value of the Ballybofey plant and machinery was devalued by around £16m between the end of 2018 and 2019.

The Glenmore plant was initially set up in 2016 to turn 25,000 tonnes of poultry litter from Northern Ireland each year into energy, supplying power to manufacturers including Bombardier and Montupet. Glenmore Generation Limited, contracted an Engineering firm Williams Industrial Services (WIS) to build the plant but in 2018, the engineering firm went into administration after cash problems caused by a contractual dispute involving a £23m project in Donegal.

The Gort Biogas Proposal is centered on feeding mostly silage to the Biogas plant which compared to food or poultry waste is an extremely costly raw material to feed biogas plants. This should certainly cast a shadow of doubt over the viability of the proposed Biogas Plant in Gort, which maybe is not quite as ‘Sustainable’ as their name suggests

Gort Biogas….the long and winding road

As we run down the clock to the 30th April, the decision due date of An Bord Pleanála on the proposed Biogas development in Gort, now perhaps is a time to reflect on the journey so far.

Three years ago, the first application was lodged by the developers with Galway County Council. The development, the largest of its kind on the Island of Ireland, was news to most people in Gort and few knew about it. However, the fire was well and truly lit during a public meeting of the Burren Lowlands Group. A concerned resident stood and addressed the room about what they thought was at stake for the towns future, its people and the environment. The battle lines were drawn and elected representatives were asked to nail their flags to the mast.

A period of quiet followed and some pondered would the people of south Galway simply allow this development to go ahead? Not a chance, the people of Gort were merely drawing breath and a groundswell of support was building. The Gort Biogas Concern Group was formed and through a series of public meetings and media campaigns the public were informed as to what the future might look like should this facility go ahead.

From the developer, we saw multiple serpentine twists and turns before a decision by Galway County Council to refuse planning, in January 2020. The thread that runs consistently throughout is that Biogas facility of this magnitude in Gort stinks, much like the sister facility in Ballybofey, Co. Galway, just ask the locals!

As in life, things work in strange ways and a global pandemic acted to strengthen the resolve of people against this development as we were all asked to stay local.  I think we all have a newfound appreciation for how lucky we are to live in south Galway and appreciate all the more the renewed sense of community.

There is simply too much at stake for the people of south Galway for the benefit of a few private investors.  So, we await the decision by An Bord Pleanála and hope that they uphold the decision of Galway County Council. Hopefully, we can soon resign this fiasco to the history books, remembered only in the Biogas song.  Regardless of the outcome, if necessary, the Biogas Concern Group will continue the fight until the job is done.

The decision date by An Bord Pleanála is the 30th of April.

Gort Biogas Resistance Flairs

The people of Gort, restricted in their ability to meet publically, continue to voice their opposition of the proposed biogas development through an art and poster campaign.  The heritage status of the town shines through with contributions from local artists and wordsmiths alike. Themes stretch from hard hitting images what the future might look like should the development go ahead, to the proud local history of the area and the importance of the local environment. Thrown in for good measure are the words of the local hero and pillar of 20th-century Irish Literature W. B. Yeats.

A painted house… down Kinincha Way

Poetry Protest!

We have our own portest poem Gort Biogas Plant vs. W.B Yeats from Leo Smyth

Biogas Begone!

A song from local Legend Niall Finnegan! (Lyrics from Richard Joyce and Niall!)

“This just shows that the resolve of the people in South Galway holds true. Too much is at stake for the people of Gort and the fragile local environment to let this development go ahead.  The impact and legacy of this development on the entire area weighted by the economic benefit to a few private developers is simply too much to ask the people to bear. One thing the global pandemic has taught us is to value our local surroundings. Local amenities such as the Gort River Walk have been a lifeline during these times.

The people of Gort fully support the decision of Galway County Council to refuse planning permission for this development and it is hoped that An Bord Pleanála uphold this ruling.

On behalf of the Gort Biogas Concerns Group, I would like to thank everybody for the support we are getting – from the artists to the sign-hangers, to the people and businesses who have supported us in our mission to stop this disastrous development

Ciaran O’ Donnell, Chair Gort Biogas Concerns Group

An Bord Pleanála’s decision is due on April 20.  

Galway Green Party Opposes Gort Biogas Proposal

The proposed Biogas Plant at Gort is very close to the Gort River and Town

The Galway Green Party lodged a submission in support of Galway County Council’s decision to refuse planning permission for the application to build a Biogas plant in the outskirts of Gort.

Aonghus Kelly from the Galway Greens stated that “The Green Party has consistently been in favour of sustainable solutions to Ireland and Galway’s energy needs in order to provide a better, safer, cleaner Gort, Galway and Ireland for all our citizens. Biogas can and should form part of the solution. However, sadly this application is far from that aim.

Frank Farrell also from the Galway Greens stated that “A flawed decision now to allow this plant would damage the town of Gort, its hinterland and cost the state and therefore her citizens large amounts of money in years to come.”

“If the Galway Green Party doesn’t support the development of a supposedly ‘Green Plant’ then it just shows the flaws in the overall proposal. “, said Ciaran O’ Donnell of the Gort Biogas Concerns Group. “Were this plant to go ahead it could have a detrimental impact on the people of South Galway, and the wonderful natural environment we live in”

The decision by an Bord Pleanala on whether or not to grant planning permission will be made in April this year.

Gort Biogas Plant vs. W.B Yeats

Wild Swans at Coole : Photo Deirdre Holmes

Mr W.B. Yeats pens a protest to the proposed biogas plant at Gort

I walked again those roads I used to see
By Coole, Kiltartan, on to Ballylee
Around, green boughs of hazel and of ash;
I thought this place was safe in the State’s care
So thought we of the Amazon – none would dare
Destroy those trees for lumber or for cash.

Here we face danger of a different sort
A planning application near the town of Gort
Presents a risk to water and to air
Twelve hundred metres from the turlough where
Upon that brimming water by the stones
I counted nine-and-fifty swans.

Was it for this that precious gift
Of nature and the gardener’s skill
On waves of chance be set adrift
With doubt of its survival still;
For this the wild bees murmur stilled,
And grassland orchid-rich no more,
Trees die with bounty unfulfilled
Squirrels grow thin, bereft of winter’s store

What need you, being men and women of good sense
A bunded tank farm with a lofty stack
Gort river walk delights without a fence
To bound the vision of Kinincha and Glenbrack
I had thought no one but a fool
Would threaten all the land from here to Coole.

Did not Ireland and Europe both decree
this is a special place we must conserve
precaution must insist that it stay free
of risk; we ask the planners vision will not swerve
but hold that what’s passed down must be passed on
the scientist and poet speak as one.

The turloughs of Raheen and Garryland
Of Lydacan, the Crannaghs and Hawkhill
Are independent of the human will
And need no guidance from a human hand
Yet as their crystal waters rise and fall
They cry out for protection from us all

A voice proclaims in our unquiet dreams
Tread softly because you tread on my streams

© Leo Smyth 2020