Author Archives: Ciaran O'Donnell

The Waiting Game continues

What’s going on with our case….?

Essentially, we have no news since our last update, and we continue to wait for a decision from ACP (formally ABP).

Those of you following progress will remember that we won our case at the High Court in August 2024. However, this wasn’t clear-cut. The developers then applied to the court for remittal. In short, this meant the developers were granted leave to have the case sent back to ABP for another review. This means a new inspector, a new report and a new decision by the board.  What a waste of time and resources.

So essentially, since August 2024, we have been waiting for news from ACP. We remain in regular contact with ACP, but nothing new to report.

In short, we could get a call tomorrow or in 12 months; we simply cannot say it’s entirely out of our control.

What happens next….?

Once we receive notification from ACP, we can plan our next move, until then, we wait. If the decision goes in favour of the developer, then we need to mobilise quickly. The community war chest provides us with the ability to respond quickly and without delay.

If the decision goes our way, then common sense will have at last prevailed. The community will then decide the next move, as agreed at our last public meeting in January 2024.

Strengthening our case

While we await a decision from ACP, we have been working in the background to increase our presence nationally and at EU level. This has been achieved through the formation of the National Biogas Concern Group Ireland (NBCG) and the gathering outside Leinster House in June, as previously reported here.

Here’s a flavour of what else we have been doing to strengthen our position:

  • November 2024. Gort Biogas Concern Group (GBCG) contributed with a “community perspective” piece to an EU-wide publication by a European NGO launched in Brussels in November 2024.
  • February 2025. The formation and launch of the National Biogas Concern Group Ireland (NBCG)
  • June, 2025. GBCG joins an EU multi-partner coalition group opposed to the rapid growth of Biomethane across Europe. The coalition produced a booklet entitled Stop the Biomethane Rush that was presented to ministers at Leinster House by the NBCG.
  • September 2025. GBCG was contacted to contribute to a research project conducted by an Irish University, as part of a wider project to evaluate the environmental, social and economic impacts of bioeconomy/bioenergy projects in Ireland.
  • October, 2025. The European Biogas Conference was recently held in Brussels (13-17 October). One of the tabled events was a panel discussion on “how biomethane is empowering communities”. A little ironic given our predicament. GBCG requested a place on this panel discussion, and of course, were refused. But they now know who we are.
  • October, 2025. The NBCG group presented at the Oireachtas Committee on Anaerobic Digestion, hosted by the Joint Committee on Agriculture and Food. The group presented the case of why it is vital to have dedicated planning regulations in place for large-scale Biogas developments and why community engagement is critical to this process. You can watch it here (opening statements begin at 44:40) and part 2 here.

So, while we await our fate, we have been busy strengthening our campaign, and we will continue with our community mandate until the threat has passed.

Have we missed anything….?

We have always operated on a Fact not Fluff policy, so when we have an update, the community will always be the first to know. GBCG is made up entirely of volunteer effort, so we keep our powder dry until we have something important to say.

If we have missed anything or if you have any other questions, we are always available, just ask. You can stop us on the street, or if you prefer, contact us directly by email at: biogasconcerngroup.gort@gmail.com or by messaging us through our Facebook page

Thank you for your untiring and unwavering support!

A harmonised voice – National Biogas Concern Group Ireland

Since 2019, the people of South Galway have stood united against the proposed construction of an industrial-scale biogas plant in Gort, Co. Galway. What began as a small but determined group of volunteers from the Gort Biogas Concern Group (GBCG) has grown into a community-driven campaign. Backed by unrelenting local support, the group has taken its fight all the way to the High Court via a judicial review of An Bord Pleanála’s planning approval.

Compare this community-led effort to the power of international agri-business investors, well-funded and backed by professional consultants. It quickly becomes clear how easily small communities can be marginalised and bulldozed by corporate interests without the support of statutory planning regulations.

A turning tide

Over the years, GBCG has assisted other community groups facing the same daunting situation we faced. These groups have in turn assisted others with their campaigns, and together using our shared experiences and knowledge we have been able to build a stronger, more coordinated response. Seven community groups across Ireland now use the moniker Biogas Concern Group, and several more exist under different names.

A harmonised voice

The need for unity saw the formation of the National Biogas Concern Group, a coalition providing a strong, harmonised voice in Ireland in response to the poorly regulated biogas boom. Led by members of the Swinford Biogas Concern Group, the NBCG mission is straightforward:

The National Biogas Concern Group, Ireland, champions the safeguarding of the environment and supports renewable energy projects that are fair and respectful of rural residents, wildlife, natural resources, and European law. We advocate for binding planning regulations for anaerobic digestion (AD) developments that ensure rigorous environmental protections, genuine community involvement, and appropriately scaled, circular bioenergy systems sited at safe distances from homes and proper road infrastructure.

The EU perspective

The National Biogas Concern Group is part of a wider European movement through our collaboration with Foodrise, a coalition that highlights the risks of the ongoing biomethane rush.

Although the biogas industry is more established in other EU countries, significant mistakes have been made. Ireland, still in the early stages of this industry, now stands on a precipice. Without strong regulation, we are poised to repeat those same mistakes, chasing unrealistic production targets at the cost of our environment and local communities.

We have already experienced breaches of planning and environmental law from existing biogas plants in Ireland due to poor regulation, monitoring and enforcement. The government’s National Biomethane Strategy aims to build 200 more biogas plants by 2030.

Leinster House – a chance to voice concerns to policymakers

National Biogas Concern Group, will meet outside Leinster House on the 11th of June 2025, to voice concerns to our elected representatives about the lack of statutory planning regulations in the face of the biogas boom.

The long and winding road

In late April 2018, a planning notice appeared on Kinincha Lane, nothing big or obvious, just a regular notice that you might see for a new house build. But this notice was different, its purpose was to inform the public that planning was sought to build one of the country’s largest biogas plants within shouting distance of the town square. What could not be foreseen was this marked the beginning of a long-running battle that would ignite the community.  The news of this new development was raised at a public meeting of the Burren Lowlands group and was met with genuine shock and surprise. How could a development of this scale reach planning and yet no one knew about it? Something was amiss. Several county councillors present at the meeting were aware of the development and were able to provide some additional details, but people were left wanting. The developers were faceless and, in the shadows, so a collective was formed to gather information.  In doing so the seeds were sown for the Gort Biogas Concern Group (GBCG), a group made up of volunteers with a simple remit; to inform the community and raise awareness about this dodgy development.

Once out in the open, news quickly spread, along with a rising tide of opposition. The new group had to work fast to be able to critically review the planning application. This was a steep learning curve. More volunteers joined the group, spreading the load. The first public meeting was held on the 17th May 2018 in Sullivans Hotel. Several hundred people attended and the message from the community was loud and clear; this development was not wanted. The size, scale and location of this plant would negatively impact all aspects of life in Gort and bring no recognisable benefits for local residents.  This wasn’t a collective case of NIMBYism (Not In My Back Yard), but genuine concerns, voiced by the community. Public information clinics were organised and over 140 objections were lodged with Galway County Council. The County planning office requested extensive further information from the developers, with a six-month deadline in which to respond. Six days before this deadline, in December 2018, the developers withdrew their planning application. The community breathed a sigh of relief, a battle was won, but was this the end?

Throughout 2018, and with the threat still looming, people began to take stock and appreciate what their local surroundings had to offer. None more so than the Riverwalk group, under the helm of David Murray. Little did we know how important this much cherished local amenity would become in the years to follow. It’s often joked that some of the credit for the Riverwalk should go to the biogas developers, so well done lads!

In November 2019, the developers lodged a new planning application, not too dissimilar to the first, but with the main entrance now located on the old Galway Road. The community rallied with renewed vigour, and a public meeting was held in Sullivans Hotel on the 10th of December, with several hundred people in attendance. Information clinics were held in Gort and Kinvara, and over 400 objections were lodged. In January 2020, Galway County Council refused planning. Another battle had been won, but we knew we were not out of the woods yet.

In February 2020, the developers lodged an appeal with An Bord Pleanála (ABP) against Galway County Council’s decision. A third public meeting was held on the 10th of March in Sullivans Hotel. With the country on the cusp of Covid lockdown, we faced another battle, while our daily lives were in turmoil. This was a gear change for the campaign, as we were now in the national arena, going head-to-head with the state’s independent planning body, ABP. Unable to meet up physically, the group was meeting weekly online to keep the momentum going. With a strong technical review team in place, GBCG submitted a detailed 54-page report to ABP including, over 1,000 petition signatures as well as a significant number of independent submissions. Over the next 10 months the case moved between ABP and the high court. Not privy to actions going on behind closed doors, our only means of keeping track was through the diligence of one of the group, who phoned ABP every week without fail. From these calls, it was gleaned that in late June ABP decided that the developer’s appeal was invalid as it was lodged after the deadline. This led the developers to lodge an appeal case in the high court. A judicial review was granted by the court and the developer won the resulting case. The upshot; the developer had another opportunity to lodge an appeal with ABP, effectively taking the case back to the beginning.  On 17th December 2020, the developer lodged a second appeal with ABP. With no opportunity to hold a public meeting, the campaign moved to social media and other creative ways to get the message out to the community. GBCG resubmitted the technical report and extensive petition in time for the 22nd January 2021 deadline. ABP advised a decision would be made by 30th April 2021.

During spring 2021, it wasn’t only the daffodils that were blooming but also the anti-biogas signs, posters, prints and car stickers around the south Galway. This led to a welcome wave of colour around Gort as well as a renewed injection of support. Having suffered the grounding effects of multiple lockdowns, our local environment was now appreciated more than ever.  

The ABP April 30th decision deadline came and went, and another response date was set for the 24th of June.   The June deadline also passed and no new date was set, leaving the community in limbo. Throughout the pandemic, the group managed to keep the campaign alive, and relevant, through the incredible efforts of the communications team. Through this effort, Gort was now in contact with several groups across the country in the same predicament. The plight of Gort had attracted the attention of local and national media outlets.  All the while the government was pushing forward with the green initiative through the national biomethane strategy. The GBCG has been consistent throughout; this technology is proven, and biomethane can help to decarbonise our economy, albeit in a relatively small proportion compared to other sources. For biomethane to be successful, developers must engage with affected communities to ensure facilities are scaled and located properly, and the benefits to the affected communities are clearly defined.  Placing the burden of industrial-scale biogas plants on small rural towns could see enormous profit potential for a few faceless investors, while the impact would be suffered entirely by local communities. This is an all-too-common scenario as applications continue to sprout across the country. The potential to make massive profits from waste, under the green flag, is one investors are keen to pursue. 

As 2021 drew to a close, the campaign was no further down the road, with no decision from ABP. The only trickle of information was from the weekly calls to ABP. Regardless, on New Year’s Day, 2022, a large group attended a community walk to the biogas site, complete with music and drums, a clear indication that the spirit of the community remained steadfast. Five months later, in May, ABP requested further information from the developer in regards to the amount of water the plant would require to operate, and where this water would come from. The group, having spent countless hours running over the planning application in fine detail had found that the numbers simply didn’t add up. It was clear this development could not be viable given the details provided. It was hoped, with the ABP request for further information that, ABP would come to the same conclusion. Autumn came and went with no updates.

On the 22nd of December 2022, after almost two years, the news came that ABP had granted permission for the development to go ahead. An unexpected thunderbolt. We now had until 22nd February in which to respond. We were fully aware this was our last chance or development would go ahead unchallenged. Action stations! Our now infamous public meeting was held on the 5th of January 2023 to raise the funds to mount our legal challenge. The goal was to challenge the decision of ABP by way of a judicial review and to have the decision overturned. This was by far the group’s biggest challenge and a challenge on multiple fronts. Within seven weeks we needed to find and secure a legal team to represent our case. Coordinating fundraising activities and fund management was critical, and we had a great team already in place to do this. From a technical aspect, a critical review of the ABP inspector’s report was required, and to do this we needed the help of external expert consultants. 

Under advice from our legal team, and in light of the government’s proposed Planning and Development Bill, we joined forces with the Burren Lowlands Group (BLL) to further strengthen our case. In doing so we closed the loop from where we started back in 2018 where BLL was first alerted to the development. The race to the finish line was tense, with papers still wet with ink being rushed up the motorway to Dublin to be filed before the court.

Throughout the spring, court dates were set, then adjourned, and the process repeated until we were granted leave to appear and then a Judicial review (JR).  A JR investigates the process by which a legal decision is made, and if the process has followed the letter of the law. Now we were solely reliant on our legal team to pursue this on our behalf. Court dates were set and then adjourned, as before. The process continued until, completely out of the blue, on the 21st of November 2023, ABP decided to concede the case. Their legal team decided they could not win the case and would cut their losses. This was a massive win for Gort. In January 2024, a public meeting was held to update the community on the news and to develop a community-led plan for the future.  It took several more months in the court for the decision of ABP to be officially overturned and the case was formally quashed. 

So where are we now? As of August 2024, the developers were granted remittal by the high court. The judge chose to bring the case back to ABP for review. A new inspector will be appointed and a new report issued to the ABP board for consideration. We are effectively back to where we were in February 2020. As daunting as this may sound, we are starting from a much stronger footing than before. GBCG submitted a highly detailed observation document, ahead of the deadline, updating the Board with the information relating to the many changes in Gort since the previous case ABP. So, as we ready ourselves to enter the battlefield again, we remain undaunted and undeterred.

The people of Gort have moved on in their thinking, setting their collective sights instead on a future with sustainable growth in mind, a place where people will want to live and work, and a place that values its local environment. These goals, developed through extensive public consultation, have been distilled into the Gort Town Centre First Plan. The Gort Town Centre First Plan does not include an industrial-scale biogas plant and indeed identifies it as a clear threat against the delivery of the plan. GBCG has a clear mandate from the community and will continue to represent the people of South Gort for as long as required.

For more information, please follow us on our Facebook page (Gort Biogas Concern Group) and visit our blog (Gort Biogas Concerns) for some interesting articles.  

A significant battle won, but the war continues

A significant win

The people of south Galway remain jubilant after their recent victory against An Bord Pleanála (ABP) during a Judicial Review in the High Court. Gort Biogas Concern Group and the Burren lowlands jointly took this action against the flawed decision of ABP to grant permission for the developers to go ahead. The legal case was funded entirely by the community and local businesses. From receiving the news in 21st Nov 2023, it took until late March 2024 for the case to be officially concluded, ending our successful Judicial Review against ABP. We will seek to have the recoverable portion of our legal costs returned to the campaign. This was a significant victory for the campaign against the national planning appeals board.

Another battle looms

The developer (not involved in the JR case but a notice party) has been granted remittal by the High Court. This means that they, the developer, does not need to restart the planning process. Instead, they can ask ABP to reconsider the same application again. One of the key points that ABP conceded on was the road realignment at the entrance of the site. Access to the site, as outlined in the application, was from the old Galway Road (R458), this road is a restricted regional road. Creating access for development of this nature onto a restricted regional road contravenes planning law. The developer is now back trying to argue the same application again with ABP, faults and all.

We are now waiting for ABP to contact Gort Biogas Concern Group, Burren Lowlands and all those who sent in observations. They must inform all parties that the application is again back on the desk of ABP. How long will this take? We don’t know. The wheels of planning law are slow, but our community is on its feet and ready for another battle.

Are we deterred? Not at all, we are in a significantly stronger position now than we were back in 2020 when the case first appeared before ABP. Are we frustrated? Yes, but we remain steadfast, with a clear mandate from the people of south Galway, underpinned by the full support of our elected representatives. We have a war chest raised by the community and this will be put to work to fight any battles that come our way. We will continue in our efforts to deter the developers from being able to create any kind of foothold in this area and we have a few things in progress and we hope to update you soon !

Thank you for your ongoing support,

Gort Biogas Concern Group

Gort Biogas Concern Group Legal Challenge Update

The people of south Galway have shown incredible generosity over the last few weeks through donations and fundraising activities. We are making good progress towards reaching our target funding to pay for our legal challenge against An Bord Pleanála.

Since receiving the notification from ABP in late December and incredible amount of work has been going on in the background to forensically review all aspects of the ABP report and to build our case.   

Legal Challenge progress

Our legal team is in place and are busy putting together our case. They are working towards a deadline of the 24th February, by which time we must submit our complete case before a judge for review. The judge will then decide if we have sufficient grounds to proceed. Once we do, then the same amount of time, roughly 8 weeks, will be offered to ABP to prepare their defence case.

The judge will then be set for the case to be heard in court.  

Time line

  • By the 24th February our legal team will have submitted the case to the High Court for leave to appeal.
  • If and when leave to appeal is granted, the judge must then offer the same amount of time (circa. 8 weeks) to the defendant to prepare their rebuttal.
  • The judge will also appoint a date for the hearing in court. This can take anywhere from 2-8 months. The length of time is difficult to estimate as extensions are invariably sought during the case. The court diary will also be busy. As always we will keep people informed as we are all fighting this together

So what’s happening right now….?

Right now we are continuing to fundraise and have some really great events coming down the track this Spring, including some fun at the St. Patrick’s Day Parade.

Keep an eye on our FB page (https://www.facebook.com/gortbiogasconcerngroup) and soon to be live Instagram account (https://www.instagram.com/gortbiogascg/) for updates and more information.

The message remains loud and clear

The people of south Galway do not want this development and will take the fight as far needs be to ensure the protection of our town, its people and our local environment.

Ciaran O’Donnell

Sustainable Bio-Energy Limited…. the numbers still don’t add up

An Bord Pleanála (ABP) recently requested further information from Sustainable Bioenergy Limited on their proposed development of a Biogas plant in Gort, Co. Galway. The ABP requested focused on the water requirements to run this facility, where this water would be sourced from, and how these numbers were calculated.  The water requirement, as stated within the application, is 120,000,000 litres per year (120,000 m3).  

The ABP request…

“Please provide a breakdown of the water/liquor supply sources to be utilized at the proposed development with the associated calculations which confirm the availability of water/liquor capacity to meet the statement requirement of 120,000 cubic metres of liquor per annum as outlined in the application documentation (Appendix 7.2 – Stormwater Report – of Volume 3 of the Environmental Impact Assessment. “

An Bord Pleanála, Further Information request

Sustainable Bioenergy Limited (via Halston) responded to on 3rd June 2022. Here we delve a little deeper into the numbers from the original application.

Let’s start at the beginning….the Gort water supply

For the last five months Gort has endured a boil water notice. Thankfully we are at the end of this long and drawn out process now and ‘normal’ service has resumed. A clean water supply is a precious commodity most of us fail to recognise until we have to sit up and pay attention. Aside from the inconvenience to most, the affect hit the more vulnerable members of our community the hardest. The underlying issue here is that the towns water supply is in a precarious position; ‘highly sensitive’ and in ‘severe crisis’, not my words, but those used in recent Dail[1] discussions about the Gort water supply.

The Gort water supply is currently close to maximum capacity and even a modest increase in demand will require significant improvements to the network. To give an understanding of capacity sensitivity, according to the Irish Water Capacity Register, in dry summers the Gort Water supply is barely able to keep up with demand. The total capacityofthe current Gort water supply is 1,440 m3 /day and the summer of 2019 saw a daily usage of 1,407 m3/day.  This doesn’t leave much of a margin before things become critical.  

Water requirements for the proposed Gort Biogas plant

Starting up a biogas plant requires feedstock and water to create a Liquor to start the Anaerobic Digestion Process. The amount of water required is dependent on the type of feedstock used and the amount dry-matter content (DMC) it contains. The water requirement calculations shown in Table 1 are based on a median 7% dilution rate, whereas actual ranges are from 5%-8%.

Table 1. Sustainable Bioenergy Limited proposed feedstock material, tonnage and water requirements for dilution.

FeedstockAnnual TonnageDry Matter Content (DMC)DMC (Tonnes)Water Content (m3)Water Required for Dilution to 7% (m3)
Grass Silage54,00028%15,12038,880162,000
Cattle Slurry22,50011%2,47520,02512,857
Agri-Food Residues13,50012%1,62011,8809,643
Total90,00019,21570,785184,500

Water requirements to meet the minimum (8%) and maximum (5%) ranges are shown in Table 2.

Table 2. Water dilution range, potential dilution requirements

DMC of digestate in digestersWater Required to Dilute Feedstock (m3 per annum)
5%294,300
6%230,250
7%184,500
8%150,188

Rain glorious rain

Sustainable Bioenergy Limited state in the EIAR that they will source all of their water requirements for the digesters from rainwater. A standard connection to the Gort water supply is included to meet building supply needs (offices, toilets, etc). Based on their own information (supplied via Halston), the plant will source most of their feedstock material from Grass Silage. This will see peak water demand during the driest months of the year.

Worth stating again…. Peak demand period for rainwater will be during the summer months when we have the least rain. The numbers provided by do not take into account the seasonality of rainfall and assume it rains equally each month of the year, throughout the year!

Whichever way you cut it once again the number simply don’t add up.

As defined in the EIAR, and taking into consideration the proposed Biogas plant feedstock inputs, process and digestate outputs there will be a significant shortfall in water supply for the plant. There is a significant lack of detail applicant’s response when it comes to water supply and demand and this simply isn’t good enough.

ABP Request for additional information…are things clearer now?

The simple answer is no. Ample opportunity was provided to address the information requested by ABP. However, all the remains is uncertainty.

“Please provide a breakdown of the water/liquor supply sources to be utilized at the proposed development with the associated calculations which confirm the availability of water/liquor capacity to meet the statement requirement of 120,000 cubic metres of liquor per annum as outlined in the application documentation

Table 3. Water demand requirements included in the original EIAR submission and if clarification has been provided in the response to ABP.

Water DemandFigures Supplied?Demand calculation clarified?
Office (kitchen toilet) for 20 people & Laboratory + 20+ truck driversNo, but potentially part of connection to the Gort mains supplyNo
Washing of facility and trucksNo, but potentially part of connection to the Gort mains supplyNo
Production start-up SeedingNo, but potentially part of connection to the Gort mains supplyNo
Fire WaterYesYes
Anaerobic Digestion processYes – 120,000 m3No
Maintenance (annual shutdown and cleaning)NoNo

Given ambiguities in the EIAR submitted in the original application, ABP were correct in questioning the numbers provided and how they were calculated. In response to the information request, we have presented our review of their submission and have highlighted the errors and miscalculations in the EIAR, while providing empirical data on current demands on the Gort water supply, highlighting the precarious state of the Gort water supply.

We can only hope that ABP will uphold the decision of Galway County Council to refuse planning permission. South Galway already has one environmental planning disaster with the Derrybrien Windfarm and the prospect of another is unthinkable. If this plant goes ahead, you may well be reminded of this bad decision every time you go to turn on the tap. Let’s not let the well run dry!


[1]  https://galwaybayfm.ie/galway-bay-fm-news-desk/dail-hears-deep-disrespect-shown-to-gort-over-boil-water-notice-saga/

If you want to send in an observation please see instructions here:

Catchment 29 – a wider perspective

Cuanbeo is a recently formed community based organisation with a mission of improving the quality of life, environment, economy and heritage in ‘Catchment 29’.  The group recently published a report (available here) on the economic assessment of the Marine Resources in southeast Galway Bay, the potential for growth and threats.

Here we look at a potential threat that hasn’t been explored- the proposal to build one of the largest Biogas plants in the country adjacent to one of the arteries feeding into inner Galway Bay. 

So what is Catchment 29?

Catchment 29 extends from Galway Docks for -117 km along the coastline to Blackhead in Co Clare. It extends inland to Athenry, Loughrea and Gort including the rivers and groundwater systems that enter the Bay. The report identifies that groundwater and surface water systems in the area are closely interlinked and highlights protection under the EU Habitats directive of areas within the catchment.

So why on earth would you site one of the largest Biogas plants in the country here given the potential consequences?

CSO map showing SAC & SPA areas around Catchment 29

Downstream effects

The report contains a case study (Case Study #3), covering a history of flooding and drainage around the Gort area, and highlights the importance of water quality entering the bay…” to the marine resources, and specifically aquaculture and fisheries in Galway Bay”. Maintaining water quality is identified as a major concern for any flood relief works being carried out. All of which are important points when trying to maintain and enhance protected and sensitive habitats.

Notwithstanding the devastating effects on the people of Gort, let’s take a look at the downstream effects of siting one of the largest Biogas plants in the country within Catchment 29.

Interconnectivity of rivers and underground flows around Gort

The proposed development lies just 10m from the Gort river, one of the main arteries that feed into the Coole-Garryland SAC. This water, in turn, enters the sea in Kinvara Bay via underground flows. Any accidental breach or discharge could potentially result in tens of millions of litres of highly concentrated effluent entering directly into the catchment system, the impact of which would be disastrous both locally and downstream. In practical terms, a facility of this magnitude is a large scale chemical factory first and foremost. For the aquaculture sites, sensitive benthic communities and protected inter-tidal habitats downstream this would be catastrophic and has the potential to not only impact the local coastal economy (fishers, aquaculture sites and the blue economy) but also threaten the protected status of this unique area.

Given the credentials of the sister development in Ballybofey (Glenmore Biogas), its chequered history of ongoing mishaps and calamities (see the Brimstone cowboys), this is a ‘when’ rather than an ‘if’ scenario.

The facility also plans to connect to Gort’s wastewater treatment plant (WWTP), a facility already identified as operating at over-capacity, placing an additional and ongoing load on an already overburdened facility. Another red flag for maintaining water quality in the Coole-Garryland SAC.   

Joined up thinking

The purpose of the report, as defined by the group, is “…to establish a baseline economic value of the marine resources including ecosystem services associated with this catchment, to heighten awareness with policy makers and planners to the true value of the aquatic marine environment…”.

The role of the wider catchment is clear- ensuring the quality of freshwater input is a vital component to maintaining water quality in inner Galway Bay. Sourcing a Biogas plant of this magnitude in such close proximity to the Gort river cannot be justified given the potential consequences.

The report notes the proliferation of community led groups in recent years, as trust waivers in state agencies to provide the degree of protection expected by communities. As custodians of our local environment, the role of community led groups has never been so important in south Galway (see South Galway-an environmental powder keg)

Three years on and the threat of this development is still very much alive. The case is now in the hands of ABP with a decision pending. Let’s hope due consideration is given not only to the implications for the people of Gort but also the downstream consequences for Galway Bay.

A glimpse into our potential future

To meet the demands of social media, the reporting of news, good or bad, has to be a fast and efficient process. To that end, I’ve been tasked to write media statements for both a positive and a negative outcome in advance of the decision by ABP. At first, I thought this would be a fairly straightforward task but as I sit to write I’m projected into two diametrically opposed futures. As with any two-party decision, there are winners and losers. Here’s a glimpse into what the future could hold…

A negative outcome

One future scenario sees a negative outcome, where ABP grants permission and the development goes ahead, I see an entire community shell shocked. People meeting on the street, shuffling awkwardly, looking at the ground, long pauses in conversation not knowing what to say. A wake-like atmosphere, as people come to terms with what lies ahead of them, a daunting, uncertain future. The loss of a loved one or in this instance a loved and cherished thing, like a community and a town irreversibly changed. The people of Gort, the losers in this future scenario, will bear the burden for future generations to come. 

An entire community reminded of the decision every time they draw a breath and inhale the shitty, eggy smell that permeates the air as far away as our beloved Coole. Reminded every time, they leave one of our many fine pubs after a great night with friends and walk home backlit by the flame stack glowing like a North Sea oil rig, higher than our church spire and visible from every quarter. Reminded every time they have to squeeze hard and pull back on a child’s hand as they attempt to cross the road between another slurry laden tanker roaring through the town. Reminded every time of the once peaceful and serene Golden Mile and Riverwalk now framed by the country’s largest slurry plant a stone’s throw from the town.

In the other camp, champagne corks pop and a few people celebrate their victory. The green light, the go-ahead, the all-clear. Excited plans are made for expensive foreign holidays, perhaps a new car or a second or even third holiday home. We won, we got one over on them, we duped the whole town. The celebration of a few to the detriment of many.

It has taken some time to write these words, for no reason other than it’s a future that’s worrying. The celebration of a few to the detriment of many.

A positive outcome

An alternative future scenario sees a positive outcome, where ABP upholds the decision of Galway County Council and permission is refused. The development is refused, quashed, flattened, a dead duck. People cross the road to confirm the news, phones are checked, messages sent. Can it be true? After a three-year fight, is it gone? Can we now move on? Corks are popped that evening, happy smiles all around. Plans are underway, a party, a celebration, a celebration of the power of people. The people of Gort, a steadfast community galvanised into action, not for personal financial gain but for the benefit of all. I can see the party in my mind’s eye, music on the riverwalk on a summers evening, laughter and chatter permeate the air, not an acrid eggy smell.  

These words flow easily, this is the future we want to see.

For now, we will have to wait for ABP to decide our fate. Let’s hope it’s for the benefit of many not the few.

Gort Biogas….the long and winding road

As we run down the clock to the 30th April, the decision due date of An Bord Pleanála on the proposed Biogas development in Gort, now perhaps is a time to reflect on the journey so far.

Three years ago, the first application was lodged by the developers with Galway County Council. The development, the largest of its kind on the Island of Ireland, was news to most people in Gort and few knew about it. However, the fire was well and truly lit during a public meeting of the Burren Lowlands Group. A concerned resident stood and addressed the room about what they thought was at stake for the towns future, its people and the environment. The battle lines were drawn and elected representatives were asked to nail their flags to the mast.

A period of quiet followed and some pondered would the people of south Galway simply allow this development to go ahead? Not a chance, the people of Gort were merely drawing breath and a groundswell of support was building. The Gort Biogas Concern Group was formed and through a series of public meetings and media campaigns the public were informed as to what the future might look like should this facility go ahead.

From the developer, we saw multiple serpentine twists and turns before a decision by Galway County Council to refuse planning, in January 2020. The thread that runs consistently throughout is that Biogas facility of this magnitude in Gort stinks, much like the sister facility in Ballybofey, Co. Galway, just ask the locals!

As in life, things work in strange ways and a global pandemic acted to strengthen the resolve of people against this development as we were all asked to stay local.  I think we all have a newfound appreciation for how lucky we are to live in south Galway and appreciate all the more the renewed sense of community.

There is simply too much at stake for the people of south Galway for the benefit of a few private investors.  So, we await the decision by An Bord Pleanála and hope that they uphold the decision of Galway County Council. Hopefully, we can soon resign this fiasco to the history books, remembered only in the Biogas song.  Regardless of the outcome, if necessary, the Biogas Concern Group will continue the fight until the job is done.

The decision date by An Bord Pleanála is the 30th of April.